Taiwan Power Company Offshore Windfarm Phase 1 Project - Demonstration
Client Taiwan Power Company Dimension / Weight 1) Deep: 18m(L) x 18m(B) x 61.88m(H) / 1081MT
2) Intermediate: 18m(L) x 18m(B) x 56.40m(H) / 1039MT
3) Shallow : 18m(L) x 18m(B) x 53.35m(H) / 984MTClass DNV Scope Fabrication of Windfarm Foundations(21 Jackets) Construction Period 1) 21±â Á¦ÀÛ ±â°£: 9.5 Month(5. Aug. 19 ? 21. May 20)
2) 1±â Á¦ÀÛ ±â°£: 8.5Month(5. Aug. 19 ? 18. Apr. 20)Sail-away 1st Shipment(4 Jackets): 2020-05-21(Thur.) / M/V Yamatai
2nd Shipment(5 Jackets):2020-05-24(Sun.) / M/V Sunshine
3rd Shipment(4 Jackets): 2020-08-16(Sun.) / M/V Yamatai
4th Shipment(5 Jackets): 2020-08-18(Wed.) / M/V Sunshine
5th Shipment(3 Jackets): 2020-09-11(Fri.) / M/V Yamatai -
Greater Changhua Offshore Windfarm 01 and 02
Client ¨ªrsted Dimension Type A : 32.2m(L) x 32.2m(B) x 67.53m(D)
Type D : 32.2m(L) x 32.2m(B) x 76.76m(D)Weight Type A : 1197.0 ton
Type D : 1235.1 tonClass DNV Scope Fabrication of Windfarm Foundations(28 Jackets) Construction Period 20 Aug, 2019 ~ 09 Aug, 2021 Sail-away Aug, 2021 ~ Oct, 2021 -
±º»ê ´ëÇü ÇØ»ódz·Â Åͺó ÇØ»ó½ÇÁõ ÁöÁö±¸Á¶¹°
Client ÀüºÏÁö¹æÁ¶´Þû/±º»ê´ëÇб³ »êÇÐÇù·Â´Ü Project ±º»ê ´ëÇü ÇØ»ódz·Â Åͺó ÇØ»ó½ÇÁõ ÁöÁö±¸Á¶¹° Á¦ÀÛ Dimension dz·Â±â: °¡·Î)35m X ¼¼·Î)33m X ³ôÀÌ)60m
±â»óž: °¡·Î)19m X ¼¼·Î)21m X ³ôÀÌ)49mWeight 1,311ton Scope dz·Â±â ¹× ±â»óž Á¦ÀÛ Construction Period Jan 2021 ~ Mar 2021 Sail-away June. 12. 2021 -
Orsted, Great Changhua 01 & 02A Offshore Sub Station(OSS), 16 skirt piles
Client KEPPEL FELS Dimension CHW01: OD)3.670m X (L)84m(8 sets, 4,001ton)
CHW02: OD)2.604m X (L)90m(8 sets, 3,591ton)Weight 7,592ton Class DNV Scope Fabrication of Pin Piles Construction Period Apr 2020 ~ Nov 2020 Sail-away 1st: Jan. 18. 2021, 2nd : Jan. 31. 2021 -
S-OIL RUG PROJECT PACKAGE #A3 MODULE PAR-01¡05
Client DAELIM Project S-OIL RUG PROJECT PACKAGE #A3 MODULE PAR-01¡05 Dimension (L) 128.8m X (B) 12m X (H) 38.62m Weight 3,608.7 ton Sail-away 10th ¡ 17th March, 2017 -
Catcher FPSO FTB
Client IHI / BW Offshore / Premier Oil Project CATCHER FPSO FTB Project Dimension (L)110.5m X (B)50m X (H)40m Weight 15,000 MT Load-out June. 23. 2016 Sail-away June. 26. 2016 -
Ichthys M06 MEG Module
Client INPEX/DSME Dimension L37 x B23 Weight Approx. 4,200 (Incl. Piping, E&I Installation) Class DNV Scope Fabrication of MEG Module Construction Period May. 2015 ~ Apr. 2016 Sail-away April. 28. 2016 -
Egina Pipe Rack Module
Client TOTAL/SHI Project EGINA FPSO PIPE RACK Project Dimension H2C: (L)32.4m X (W)6.8m X (H)24m(413ton)
H2D: (L)37m X (W)6.8m X (H)25.4m(551ton)
H2G: (L)32.6m X (W)6.8m X (H)24m(430ton)
H2 : (L)35.5m X (W)6.8m X (H)24m(419ton)Weight 1,813 MT Class DNV Scope Fabrication of Pipe Rack Module Construction Period Jul 2015 ~ Jun 2016 Sail-away July. 6. 2016 -
PFLNG2 Flare Derrick Module
Client JGC Scope Engineering, Procurement and Construction (EPC) of PFLNG2 Flare Derrick Module Weight 1,747 MT Construction Period Apr. 2015 ~ Dec. 2016 -
Jangkrik FPU
Client ENI / HHI Scope Cutting, Assembly, Painting, Outfitting, P.E, and Transportation of Forward Ship Block Weight 4,352 MT Construction Period Mar. 2015 ~ Sep. 2015 Load out Dec. 24. 2015 -
Badamyar
Client TOTAL E&P Myanmar / HHI Scope LCP Jacket and Piles, WHP4 Jacket and Piles & Bridge Jacket Weight 8,829 MT Construction Period Mar. 2015 ~ Jan. 2016 Load out Jan. 17. 2016 -
Catcher FPSO MMB
Client BW Offshore / IHI Weight 19,795 MT Scope Fabrication of MMB (Middle Mega-Block) and FTB (Fore Terra Block) Load-out Dec. 8. 2015 -
Shell Prelude FLNG
Client Shell / SHI Dimension 55M x 50M x 42M Weight 900 MT Class Lloyd Scope M6 Turret Gantry Structure Construction Period Jan. 2014 ~ Dec. 2014 -
Booster Compression
Client Carigali HESS / HHI Dimension 48M x 48M x 55.4M Weight Jacket 6,304 MT / Piles 3,847 MT Construction Period Oct. 2013 ~ Jan. 2015 -
lchthys FPSO Driven Pile
Client INPEX / DSME / SHI Dimension OD 5,500 x L 63,600 Weight 16,140 MT(460 MT each) Section Quantity 37 Driven Piles -
Ichthys FPSO Turret BSS
Client INPEX / DSME Dimension OD 22,000 x H 6,450 Weight 445 MT Construction Period Oct. 2013 ~ May. 2014 -
Ichthys CPF
Client INPEX / SHI Section Pontoon Block Weight 3,100 MT Dimension 50M x 27M x 12M Construction Period Apr. 2013 ~ Feb. 2014 -
P2045, P2046 and P2053
Client PPL Shipyard Singapore Section 10 Living Quarter Blocks, 6 Wing Tank
Blocks and 2 Leg Well BlocksWeight Total 18 blocks: 2,070 MT -
Bigfoot TLP
Client Chevron / DSME Weight 4,635 MT Dimension 120M x 120M x 65M Section Pontoon Block and Top Frame fabrication -
OFON 2 T&I
Owner Technip Weight 3,800 MT Construction Schedule Jul. 2011 ~ Sep. 2012 Section Substructure and grillage for modification and refurbishment -
3MW ÇØ»ódz·Â¹ßÀü ÇϺα¸Á¶¹° Á¦ÀÛ°ø»ç
Owner µÎ»êÁß°ø¾÷ Construction Schedule 2011³â 1¿ù ~ 2011³â 4¿ù Section JACKET ( PIN PILEÆ÷ÇÔ), DECK 6±â -
RongDoi(Vietnam) PLEM
Owner KNOC / HHI Weight 210 MT Construction Period Nov. 2006 ~ Dec. 2006